Major Schedule Change -- No Parking instructions for 9/29 - 9/30

Post date: Sep 29, 2014 1:09:42 AM

All remaining roads in CJG, including the East Side, will get the first layer of asphalt paving this Monday and Tuesday. This is a change from the notice that was sent out Thursday night.

No Parking or Driving 7 a.m. – 5 p.m.

Please avoid scheduling deliveries Monday and Tuesday if at all possible.

Ericsson Road might be closed completely for short periods of time on Tuesday.

If your car is parked in the Community House lot, you may leave it there only if you are sure you will not need to get it out between 7 and 5. If you think you may need to get your car out of CJG at some particular time between 7 and 5, you should park it across MacArthur Blvd. (or on Ericsson, McKay, Russell, or Thorne – Monday only) before 7am.

Please see attached map of no-parking areas for this week.

Monday, Sept 29 – (red section)

  • All of Froude Circle, including cul-de-sacs

  • Webb Rd

Parking available on Ericsson East and West, McKay, Russell, Thorne; limited access to Community House lot

Tuesday, Sept 30 – (green section)

  • Ericsson Road East and West

Parking on McKay, Russell, Thorne, Webb, Froude; entry and egress limited