NO PARKING schedule for week of 9/15 - 9/19

posted Sep 13, 2014, 6:07 PM by Neele Johnston   [ updated Sep 13, 2014, 6:07 PM ]
To: All Members

PAVING WORK SCHEDULE – 9/15 – 9/19
ERICSSON WEST RESTRICTIONS AFFECT ALL MEMBERS
PLEASE READ CAREFULLY

Monday 9/15 from 7 a.m – 5 p.m.     
Ericsson Road West – CLOSED again from Webb to Russell –                
During this time:
  • No parking or driving on this part of Ericsson (green highlight on drawing).
  • Only way in and out of West side of CJG is Webb Road (drive slowly!)
  • Please avoid parking on Webb Road if possible during work period to allow cars to enter and exit safely.

Tues 9/16 – Wed 9/17 from 7 a.m. – 5 p.m.  
Ericsson Road West – one lane access on Ericsson from Webb to Parkway entrance.  Webb closed. 
During this time:
  • No driving or parking on Webb or this (top) section of Ericsson (blue highlight on drawing). Please park your car on McKay, Russell, Thorne, or the east side of CJG.
  • Please do not schedule deliveries to Webb Rd. addresses.
  • Webb Rd. will be entirely closed for paving during the 7-5 time period. Some traffic will be able to pass on one side or the other of this section of Ericsson.

Thurs 9/18 – Fri 9/19 from 7 a.m. to 5:00 p.m. 
Both Cul-de-sacs on Froude Circle will be closed Thurs 9/18 – Fri 9/19 from 7 a.m. to 5:00 p.m.   
No parking or driving on the cul-de-sacs.

Thank you for your patience and cooperation!